Steady progress on 18-month job to dismantle oil platform
PROGRESS made on decommissioning an oil rig in Lerwick over the last few months may be “look quite boring” from the outside – but it is “utterly essential”.
That is according to Brown and Mason, the specialist contractors tasked with dismantling the North Cormorant platform which was brought to Dales Voe in August.
PR and marketing manager Alex Ellison said work since then has focused on making sure staff can safely get onboard the huge structure.
“It’s access and it’s make safe, that’s the two main priorities over the last few months,” he said.
“So it’s getting on board, making sure we can get to it, and making sure it’s safe for our guys to go on and work.”
After that work might include the likes of “soft stripping”, or removing non-structural items, and identifying hazardous materials.
The project to dismantle the TAQA oil rig – which weighs more than 16,000 tonnes – will take around one and a half years to complete, with logistics firm Peterson also supporting the effort.
At the moment there are 16 people working on site, and this number will fluctuate depending on the stage of the project.
Speaking at the project’s latest community engagement in Lerwick on Wednesday, Ellison said Brown and Mason would seek to employ locally where possible.
He also said the company would try to use local solutions for disposing waste materials where possible, such as the scrap metal merchant, but given the volume of material involved this will not always be possible.
The plan is for at least 97 per cent of the material to be recycled.
The topsides were removed northeast of Shetland in a single lift by Allseas’ massive Pioneering Spirit vessel – the largest of its kind in the world – before being taken to Dales Voe.
Help keep Shetland’s news open to everyone
Good local journalism takes time, care and people on the ground. Membership helps us keep reporting the stories that matter to Shetland — and keep them free for everyone to read. Members get a weekly newsletter created especially for them, local ads only, and can bookmark stories and join the conversation in the comments.
The Northern North Sea platform achieved first oil in February 1982 and went on to produce more than 467 million barrels of oil over more than four decades of operations.
It is Lerwick Harbour’s largest decommissioning project to date.
The platform’s jacket, which weighed 8,500 tonnes, then followed in 2022.