A £24 million capital dredging project in Lerwick Harbour has now been completed, with one million tonnes of materials removed to deepen and widen the area.
Lerwick Port Authority hailed the project’s completion as a major milestone in the largest capital investment in the port’s modern history.
The operation involved a specialist fleet of dredging and support vessels, with final checks completed ahead of the departure of the main vessels on 31 October.
In total, the two phases involved the removal of soft seabed material and hard rock, with material disposed of north of Bressay.
The dredging work has been carried out to deepen and widen key parts of the harbour, increasing capacity for larger vessels and supporting future growth across Shetland’s fishing, cruise and offshore industries.
Lerwick Port Authority chief executive Captain Calum Grains said the completion of the works marks a “significant milestone for Lerwick Harbour”.
“This project has been about ensuring we have the infrastructure and capacity to meet the changing needs of the industries we serve,” he said.
“By improving access and accommodating larger vessels, we are creating new opportunities across several key sectors while strengthening Lerwick’s role in supporting Shetland’s economy.
“Delivering a project of this scale within a busy working harbour has required considerable planning and collaboration.
“We are grateful to everyone involved in bringing the marine works to a successful conclusion.”
The dredging works have widened the North Ness Channel to 140 metres and deepened it to 10 metres, while providing a continuous 10-metre berth depth along the 275-metre Mair’s Pier and improving the approaches to Gremista Quay.
At Dales Voe, dredging has increased the depth adjacent to the quay to 14.5 metres, with approaches deepened to 16 metres.
The work has enhanced the harbour’s ability to accommodate larger offshore vessels with the port authority saying it will strengthening Lerwick’s position in the offshore industry.
Help keep Shetland’s news open to everyone
Good local journalism takes time, care and people on the ground. Membership helps us keep reporting the stories that matter to Shetland — and keep them free for everyone to read. Members get a weekly newsletter created especially for them, local ads only, and can bookmark stories and join the conversation in the comments.
For the fishing sector, improvements will enable future infrastructure quay developments at Gremista to support pelagic sector capacity, it said.
The cruise sector will also benefit from improved navigational access through the North Ness Channel and central basin, creating potential opportunities for larger cruise ships to use the 275-metre quayside.
The project was managed by Arch Henderson, with specialist contractor Boskalis Westminster Ltd undertaking the dredging works.
Arch Henderson senior consultant Andy Sandison said they were “delighted” to have been a major part of the project.
Boskalis Westminster managing director Paul de Jong said they were “proud to have completed a second major dredging project” for Lerwick Port Authority.
“Working closely with the teams at Lerwick Port and Arch Henderson, we successfully delivered a challenging scheme to deepen the North Harbour and Dales Voe,” he said.
“We look forward to the opportunity to work in Shetland again in the future.”
The project was supported by Bank of Scotland and Scottish Government agency Highlands and Islands Enterprise.
Shetland News visited the project in September 2025 in its earlier stages, which you can read here.