News / Viking Energy wins land court case
THE SCOTTISH Land Court has granted Viking Energy permission to build a 103-turbine wind farm on crofting land in the north mainland of Shetland.
The decision was made public on Tuesday afternoon following a four-day long hearing of the land court in Lerwick in early July.
Opponents to the development said the decision by the land court was “not entirely unexpected but disappointing nevertheless” while the developer welcomed the judgement and added it would comment more fully once a written judgement had been made available by the court.
The land court said it was satisfied by the case presented by Viking Energy and felt that “the evidence led by the respondents at the hearing does not, in the court’s view, provide a basis upon which the application can properly be refused”.
The court said that it would not issue a formal order at this stage as otherwise the appeal days would begin to run. It will be issued along with the court’s full written statement, which is likely to be in several weeks time.
In its short statement, the land court also said that it recognises that the outcome would be deeply disappointing to the four respondents to the Viking application, and added that it “has to apply the law as it understands it.”
“The court wishes, nevertheless, to record its respect for the sincerity and strength of the respondents’ feelings in relation to the perceived impact of the proposed development and thank them for the civility with which they presented their arguments at the hearing,” it said.
Sustainable Shetland vice chairman James Mackenzie, who represented two of the respondents, said the decision was not unexpected.
He said the respondents had not yet made up their mind whether or not to appeal the decision.
He added: “We appreciate that the court has expressed its respect for the dignity and sincerity in which the respondents put forward their case.”
Become a supporter of Shetland News
Viking project manager Aaron Priest said: “Viking Energy Wind Farm LLP has been advised by the Scottish Land Court that a decision has been made to grant its sec 19A application.
“We welcome the Court’s decision. Viking Energy Wind Farm LLP will await the full written judgement of the court before commenting further.”
Become a supporter of Shetland News
Shetland News is asking its many readers to consider start paying for their dose of the latest local news delivered straight to their PC, tablet or mobile phone.
Journalism comes at a price and because that price is not being paid in today’s rapidly changing media world, most publishers - national and local - struggle financially despite very healthy audience figures.
Most online publishers have started charging for access to their websites, others have chosen a different route. Shetland News currently has over 600 supporters who are all making small voluntary financial contributions. All funds go towards covering our cost and improving the service further.
Your contribution will ensure Shetland News can: -
- Bring you the headlines as they happen;
- Stay editorially independent;
- Give a voice to the community;
- Grow site traffic further;
- Research and publish more in-depth news, including more Shetland Lives features.
If you appreciate what we do and feel strongly about impartial local journalism, then please become a supporter of Shetland News by either making a single payment or monthly subscription.