Power station standby plans on schedule for end of 2026

LERWICK Power Station remains on track to move into standby mode at the end of the year, according to SSEN.

It comes after “good progress” was reported on the installation of a nearby battery storage system, which is a key element of the plans.

The 68MW development is part of SSEN’s plans to put the diesel-fuelled Lerwick Power Station in standby mode once the isles’ local network is connected to the national grid via the subsea HVDC cable, expected later this year.

SHEAP headquarters with the Lerwick Power Station in the background. Photo: Shetland News

The Wartsila batteries – which will be able to absorb excess renewable energy – would help to keep Shetland’s lights on while the power station comes out of standby mode, which could take up to 45 minutes.

The power station would need to move out of standby in the event of planned or unplanned outages on the HVDC cable.

Earlier this year SSEN also reported that work on the new Kergord to Gremista electricity transmission link had completed – another key feature of the standby project.

Spanning 22km across overhead lines and underground cables, the 132kV connection provides a secure transmission route between a new Gremista grid supply point and the Kergord substation, where the subsea HVDC link connects to Shetland.

When asked for an update on the plans to put Lerwick Power Station into standby, SSEN said a comprehensive schedule of testing and commissioning will begin once construction of the battery system and associated infrastructure is complete.

Once this programme is completed and the Gremista site is operational, the power station will be able to move into standby.

This has previously experienced delays, with hopes in 2021 that the power station would go into standby in late 2024, for example.

The power station’s capacity stands at more than 70MW, and it was built in 1953.

The Kergord-Gremista project is separate to SSEN’s ongoing Shetland north reinforcement work, which is the cause of the many traffic lights on the A970 and Dales Lees roads in recent months.

Become a member of Shetland News

Shetland News is asking its readers to consider paying for membership to get additional perks:

  • Removal of third-party ads;
  • Bookmark posts to read later;
  • Exclusive curated weekly newsletter;
  • Hide membership messages;
  • Comments open for discussion.

If you appreciate what we do and feel strongly about impartial local journalism, then please become a member of Shetland News by either making a single payment, or setting up a monthly, quarterly or yearly subscription.

 
Advertisement 

Sign up
for our Newsletters

Stay in the loop with newsletters tailored to your interests. Whether you're looking for daily updates, weekly highlights, or updates on jobs or property, you can choose exactly what you want to receive.

Advertisement 
Advertisement 
Advertisement 
Advertisement 
Advertisement 

JavaScript Required

We're sorry, but Shetland News isn't fully functional without JavaScript enabled.
Head over to the help page for instructions on how to enable JavaScript on your browser.

Interested in Notifications?

Get notifications from Shetland News for important and breaking news.
You can unsubscribe at any time.

Interested in Notifications?

You can install the Shetland News app on your device, simply tap and then 'Add to Home Screen'.

Loading the app will allow you to accept notifications.

Have you considered becoming a member of Shetland News?

  • Removal of third-party ads;
  • Bookmark posts to read later;
  • Exclusive curated weekly newsletter;
  • Hide membership messages;
  • Comments open for discussion.