widget/exchange-29
widget/exchange-30widget/exchange-33
widget/exchange-31

Climate / Subsea cable very reliable, says project director

Potential benefits of 5G technology for construction industry to be trialled from next month

The Kergord converter station construction site seen from the Mid Name ridge. Photo: Dave Donaldson for SSE Renewables

THE PROJECT director in charge of building the Kergord converter station and 600MW interconnector infrastructure linking Shetland to the national grid expects the subsea link to be available for 99.8 per cent of the time.

Reacting to concerns voiced locally about the reliability of high voltage direct current (HVDC) subsea cables and the potential consequences of long outages, SSEN Transmission project director John Scott said the company would do everything they could to protect the cable.

“We devote a lot of effort to ensuring that the cable is as much protected as possible, from the initial design, the routing, and the burying and protection of the cable,” he told Shetland News during a visit to the Kergord construction site on Thursday.

SSEN Transmission project director John Scott. Photo: Hans J Marter/Shetland News

He added: “The cable itself is double-wired armoured, so there is physical protection built into that cable to avoid damage from dragging or snagging by fishing gear.

offset-carousel/post-mobile/0

“The cable is then fully buried, so it is fully protected end to end, and on the seabed we achieve that by trenching the cable in about one metre deep.

“Where seabed conditions won’t allow that trenching we will protect the cable with rock to provide a sufficient level of protection.

“In our experience with the Caithness to Moray cable – the most directly relevant one, which we installed in 2018 – we had no issues at all with the cable being damaged or being out of service.”

Lerwick Power Station will remain on standby, should the cable fail, until at least 2035.

“[We have] 99.8 per cent availability of the link; not just the cable, but all the hardware at both ends,” Scott added.

That hardware is currently being built at the site high up in the Kergord valley and along the westside of the valley in preparation for the cable being laid to the landfall site at Weisdale Voe.

Become a supporter of Shetland News

 

With the large concrete platform almost complete, rapid progress is being made in erecting the steel works for the main reactor hall – described as the “heart of the site”.

The main reactor hall is taking shape. Photo: Malcolm Younger for Shetland News

That large building is scheduled to be wind and water tight by December. Due to Shetland’s demanding weather conditions all equipment will be housed inside.

Scott confirmed that the core of the site was constructed with a 40-year lifespan in mind.

Once operational in 2024 to coincide with the expected completion of the Viking Energy wind farm, the converter station will have capacity left for other renewable energy developments, such as the two Peel Energy owned wind farm projects outside Lerwick and in Yell.

offset-carousel/post-mobile/1

But the station could also be the base for delivering electricity elsewhere. Scott confirmed that SSEN transmission has had some early discussions with the Orion clean energy project which hopes to facilitate the decarbonisation of offshore oil and gas installations west of Shetland.

While such discussions are at a very early stage, he said that supplying green electricity north to power oil installations was something the converter station could potentially do.

“They [Orion] are in discussion with ourselves and [SSEN] Distribution around various potential plans around decarbonisation and onshore power connections, but it is at a very early stage in terms of those discussions, and we are effectively waiting on proposals from the oil and gas industry as to what they want or propose,” Scott said.

“There is capacity here [at Kergord], it’s certainly built with a degree of flexibility so that we can either connect sources of electrification or we can supply energy.”

offset-carousel/post-mobile/2
Student engineer Aisling Elliott demonstrating the advantages of augmented reality technology where the building under construction becomes visible. 5G will further enhance those abilities. Photo: Malcolm Younger for Shetland News

Meanwhile, trials with cutting edge technology will get under way in the remote Kergord valley next month when a 5G private network will be switched on to monitor progress using cameras, drones and mixed reality.

Earlier this year, main contractor BAM Nuttall was granted government money under the 5G Create programme.

The company hopes to learn from the pilot around how best to utilise the new technology in the construction industry to make the planning and the construction of buildings easier.

offset-carousel/post-mobile/3

Apart from rapid data transmission and streaming, the technology could also lead to machinery being operated remotely.

Scott said local company Shetland Flyer was involved in the project.

“At the moment we are using their drones to record footage. It takes a day or so to process and circulate it around the team,” he said.

“With 5G we will have a live stream to the designers in Sweden, or wherever, and engage with them in real time, and resolve things in real time.”

Become a supporter of Shetland News

Shetland News is asking its many readers to consider start paying for their dose of the latest local news delivered straight to their PC, tablet or mobile phone.

Journalism comes at a price and because that price is not being paid in today’s rapidly changing media world, most publishers - national and local - struggle financially despite very healthy audience figures.

Most online publishers have started charging for access to their websites, others have chosen a different route. Shetland News currently has  over 600 supporters  who are all making small voluntary financial contributions. All funds go towards covering our cost and improving the service further.

Your contribution will ensure Shetland News can: -

  • Bring you the headlines as they happen;
  • Stay editorially independent;
  • Give a voice to the community;
  • Grow site traffic further;
  • Research and publish more in-depth news, including more Shetland Lives features.

If you appreciate what we do and feel strongly about impartial local journalism, then please become a supporter of Shetland News by either making a single payment or monthly subscription.

Support us from as little as £3 per month – it only takes a minute to sign up. Thank you.

 
widget/pd_widget-6widget/pd_widget-7widget/pd_widget-8widget/pd_widget-9

Newsletters

Subscribe to a selection of different newsletters from Shetland News, varying from breaking news delivered on the minute, to a weekly round-up of the opinion posts. All delivered straight to your inbox.

Daily Briefing Newsletter Weekly Highlights Newsletter Opinion Newsletter Life in Shetland Newsletter

JavaScript Required

We're sorry, but Shetland News isn't fully functional without JavaScript enabled.
Head over to the help page for instructions on how to enable JavaScript on your browser.

Your Privacy

We use cookies on our site to improve your experience.
By using our service, you agree to our Privacy Policy and Cookie Policy.

Browser is out-of-date

Shetland News isn't fully functional with this version of .
Head over to the help page for instructions on updating your browser for more security, improved speed and the best overall experience on this site.

Interested in Notifications?

Get notifications from Shetland News for important and breaking news.
You can unsubscribe at any time.

Become a supporter of Shetland News

We're committed to ensuring everyone has equitable access to impartial, open and quality local journalism that benefits all residents.

By supporting Shetland News, you play a vital role in ensuring we remain a pivotal resource in supporting the community.

Support us from as little as £3 per month – it only takes a minute to sign up. Thank you.